Wester Kittochside Farm, National Museum of Rural Life, East Kilbride

Working farm conservation:

Wester Kittochside

East Kilbride · 2026

Our role
Principal contractor and specialist conservation contractor
Client
National Trust for Scotland
Operator
National Museums Scotland (National Museum of Rural Life)
Contract administrator and principal designer
Adams Napier Partnership
Value
Under £0.5m
Programme
Phase 1 October 2025 to February 2026; Phase 2 June to September 2026
Scope
Reslating, rooflight overhaul, skew copes and fillets, lime repointing and limewash, leadwork, joinery repairs and external decoration
Site
Working dairy farm and public visitor attraction, open throughout

Wester Kittochside is the historic farmhouse and steading at the heart of the National Museum of Rural Life in East Kilbride. Owned by the National Trust for Scotland and run by National Museums Scotland, it is still a working farm, with a dairy herd milked daily in front of visitors. Over two phases, with Adams Napier Partnership as contract administrator, we carried out the external fabric repairs to the West Range in 2025 to 2026 and then to the East Range and byres in 2026, while the farm kept working and the museum stayed open every day.

Before & after

Drag across the image to compare the building before our work and after completion.

Wester Kittochside Farm after restoration by LTM GroupWester Kittochside Farm before restorationBeforeAfter

The challenge

The roofs were heavily mossed, the slates and their fixings were failing, skew copes had open joints and tired mortar fillets, and the rubble walls needed raking out and repointing in lime. The real test was the setting. This is a working farm with livestock moving between fields and byres, a milking routine that cannot stop, and a steady stream of visitors, families walking the farmyard. Every lift, delivery and scaffold change had to fit around animal movements, milking times and opening hours, without ever putting the public or the herd at risk.

Our solution

We planned the works around the farm, not the other way round. Before each phase, programme and access arrangements were agreed with the museum team, and our site manager joined the daily operations meeting so works were planned around animal movements and milking. Deliveries were timed between the milk lorry leaving and the museum opening, livestock routes and gates were kept clear, and our operatives stayed out of livestock enclosures. The working areas were enclosed with Heras fencing, hoarding and debris-netted scaffold, giving visitors a clear, signed route through the courtyard, and visitor handwashing points were kept available near the animals. To keep the buildings dry while the roofs were open, we erected a temporary roof on the scaffold over the whole structure, so the stripped roofs, sarking and new membrane were protected from rain and the work carried on through poor weather without risk of water getting in. On the roofs, slate courses and diminishing coursing were recorded before stripping, the slates were set aside and relaid on a new breathable underlay with the original coursing kept, the rooflights were overhauled and refitted, and new lead flashings were formed. Skew copes were repointed with new lime mortar fillets. The walls were raked out and repointed in lime, with deep packing to voided joints and the new pointing cured under damp hessian, and finished in three coats of limewash. Doors were overhauled, with new timber made at our own yard, and the rainwater goods, windows and doors were redecorated.

Wester Kittochside Farm

“It all looks great and we're really pleased with how this project turned out. Thanks to everyone at LTM for their hard work on this!”

Brigit LuffinghamBuilding Conservation Surveyor, National Trust for Scotland

Outcomes

A farm that never stopped

Milking, livestock movements and visitor access carried on every day across both phases.

Visitors kept safe and welcome

Fenced, netted and signed working areas kept the public clear of the works while the courtyard stayed open.

Weathertight, whatever the weather

A temporary roof kept the opened roofs dry throughout; they were then reslated on the original coursing, with skews and lead renewed and the walls repointed and limewashed in lime.

← All projects