Asknish House, Lochgair, Argyll and Bute

Restoring Asknish House with Expertise and Dedication:

Asknish House

Argyll and Bute · 2022

Our role
Principal contractor
Client
Private client
Architect
Simpson & Brown
Programme
October 2019 to May 2022 (Phase 3 interiors)
Scope
Structural timber and rot repairs, reroofing in salvaged and new slate, leadwork, lime pointing, lime harling and limewash, decorative stone repairs, lath and lime plaster repairs, insulating lime plaster, cast cornice and ceiling reinstatement, sash and case windows, panelling, shutters and joinery repair and reinstatement, internal doors, stove installation, wall and floor tiling, building services
Awards
Georgian Group Architectural Awards 2022: winner, Rescue of a Georgian Building. Argyll and Bute Design Awards 2023: winner, Built Heritage

Asknish House is a five-storey Georgian Palladian mansion at Lochgair on Loch Fyne, built in the late 18th century and listed Grade B. It served as a safe house during the Clydeside Blitz in the Second World War, then stood empty for around twenty years. Working with conservation architects Simpson & Brown for private owners, we restored the house over several phases as principal contractor, repairing the external fabric first and then carrying out the full internal restoration and fit-out that brought it back into use as a family home built to passive house principles. Practical completion of the interior phase was certified in May 2022. The restoration went on to win Rescue of a Georgian Building at the Georgian Group Architectural Awards 2022 and the Built Heritage category at the Argyll and Bute Design Awards 2023.

Before & after

Drag across the image to compare the building before our work and after completion.

Asknish House after restoration by LTM GroupAsknish House before restorationBeforeAfter
Asknish House: interior walkthrough

The challenge

Two decades of neglect had let water into the house and rot ran through all five storeys. Many floor joists, beams and roof timbers had failed, and the three timber floors and the roof had to be propped throughout before any repair could start. Decorative plaster ceilings and cornices were at risk of collapse, and much of the original joinery was decayed. The brief added a further layer: to keep as much historic fabric as possible while achieving a high standard of airtightness, insulation and ventilation in a solid-walled 18th century building, without harming its character.

Our solution

Working with the structural and temporary works engineers, we propped each floor and the roof, then inspected every joist and timber element individually, repairing where we could and replacing only what had failed. Where primary timbers were beyond repair, new steel beams were installed on concrete pads. The roof was recovered in a mix of salvaged and new slate, with new leadwork to flat roofs and parapet gutters and new cast iron rainwater goods. Externally the walls were lime pointed, lime harled and limewashed, and the decorative stone dressings conserved. Inside, the at-risk ceilings were consolidated and held in place, lath and lime plaster repaired, and missing cornice, frieze and ceiling rose sections cast in our own workshop from moulds taken off the original work. External walls received a thermally insulating lime plaster system and new sash and case windows were taped into the plaster reveals for airtightness, tested at stages through the job. Shutters, panelling and architraves were recorded, removed, labelled and stored, then repaired and refitted. The house was fully rewired and replumbed, with heat recovery ventilation, underfloor heating and a biomass boiler. The final interior phase ran from October 2019 and was completed floor by floor from the attic down. Plastering ran through the whole interior, including the main and rear stairs and cupboard linings. Cornices and pediments were fitted, and our joiners made and fitted wall panelling, window linings and shutters, doors, dado and picture rails, oak shelving and vanity units, with stone and engineered oak floors laid by specialist floor contractors. Wood-burning stoves were installed in the drawing and sitting rooms with protective frames, and wall and floor tiling was completed to the bathrooms and utility areas. The new rooflight and oculus, external limewash and slate repairs were finished and the whole building was airtightness tested, with the certification issued to all parties, before handover.

Asknish House

“The building was in a perilous state and close to collapse from rot but is now safe and watertight thanks to their skill. In conjunction with the conservation architect they have been proactive in providing solutions to the inevitable unexpected problems arising in this type of project. Overall, the quality of all the workmanship at LTM is exemplary and the pride that their craftsmen and women take in it is shared by us.”

The ownersPrivate client, Asknish House

Outcomes

A rescued listed house

A derelict, rot-damaged Georgian mansion made structurally sound, weathertight and lived in again.

Original fabric kept

Historic timbers, ceilings, cornices and joinery repaired and reinstated rather than replaced wholesale.

Finished interiors

Plastered, panelled, tiled and decorated rooms, with stoves, shutters and joinery fitted, handed over at practical completion in May 2022.

Award-winning conservation

Winner of Rescue of a Georgian Building at the Georgian Group Architectural Awards 2022, and of the Built Heritage category at the Argyll and Bute Design Awards 2023, where the judges recognised the careful restoration of the house combining traditional materials with modern technologies.

← All projects

Have a similar building?

Tell us about it and we’ll come back to you with how we’d approach it.

Aldourie Castle, Inverness

Next project

Aldourie Castle

Inverness