Stone repair and lime harling:
38 Ardconnel Street
Inverness · 2015
38 Ardconnel Street is a stone building in Inverness that was being converted to flats for A R Briggs & Co. McGregor Construction (Highlands) Ltd, the main contractor, appointed us to deal with the external masonry, working to the design of Colin Armstrong Associates, Chartered Architects. Our work covered the removal of cement render and pointing, repair of the stonework behind it, and the reinstatement of the walls in lime.






The challenge
The walls had been covered in cement render and pointed in cement, which holds moisture in the masonry and was breaking away from the stone. Behind it, the wall faces were a mix of rubble and dressed red sandstone, with defective lintels and rybats around the window openings. All of this had to be exposed, assessed and made good before any new finish could be applied. The work was carried out from scaffold, with the windows and drains protected throughout.
Our solution
Cement render was removed using hand tools, with light breakers where appropriate, and cement pointing was cut out until sound lime mortar was reached. Original pinning stones were salvaged and set aside for reuse. Protection boards were laid on the scaffold lifts to catch debris, which was cleared daily, and each elevation was worked top down and washed down with clean water on completion. Defective stone around the openings was repaired or replaced, and joints were raked out by hand with hammer and chisel and repointed in a pre-mixed lime mortar, struck to a consistent texture and protected from weather as it set. Where the wall was to be harled, deep voids were first packed out with pinnings and flushed up. A straightening coat of about 10mm was applied, pressed back once set and keyed with the back of the trowel, followed after a couple of days by a flicked texture coat of 6 to 8mm. The harling was then finished with an approved limewash, and the architect asked us to propose a colour to suit the stone.
Outcomes
Cement removed from the walls
Failed render and cement pointing were taken back to sound masonry, allowing the stone to be assessed and repaired.
Stone repaired and reused
Defective stonework was dealt with and original pinning stones were kept for reinstatement.
Breathable lime finish
Lime pointing and harling with a limewash finish replaced the cement coverings.
Have a similar building?
Tell us about it and we’ll come back to you with how we’d approach it.
One of 1,000+ projects
More schools, libraries & commercial
- 163 High Street, ElginCase study →
- 186 Argyle Street, GlasgowCase study →
- 96 Academy Street, InvernessCase study →
- Bank of Scotland, AberfoyleCase study →
- Castle Street, Forfar (consultancy)Case study →
- Cromwell Tower, AberdeenCase study →
- Eastern Residences, Broughty FerryCase study →
- Georgian Steps, George SquareCase study →
- Golf Tavern, EdinburghCase study →
- Hillside SchoolCase study →
- King's College, AberdeenCase study →
- Marischal College, AberdeenCase study →

Next project
Tullibody Lychgate
Tullibody